Krebs was contracted by the Alabaster Water Board to evaluate and design membrane filtration for 2.5 MGD capacity at the Well No. 3 Water Treatment Plant. The well was deemed under the influence by ADEM based on solids. The project consisted of issuing a request for proposal for membrane filtration, evaluating the proposal, and designing the improvements. The project included a new administration/lab area, electrical room, chemical feed improvements, and filter building.
Alabaster, AL
Alabaster Water Board
$3,200,000
Complete